My contractor disappeared halfway through the remodel. What do I do?
The statutes do not count a number of missed days. They name abandonment and a failure to keep going with reasonable diligence. This page says what CSLB and the code say you can file. It does not say you will get money back.
The statutes do not count missed days
Section 7107 says abandonment without legal excuse of any construction project the licensee undertook as a contractor is a cause for disciplinary action. Section 7119 says a wilful failure or refusal, without legal excuse, to prosecute a construction project with reasonable diligence, causing material injury to another, is also a cause for disciplinary action. Section 7113 says a failure in a material respect to complete the project for the price stated in the contract, or in any modification of it, is a cause for disciplinary action.
None of those sections says that a set number of days without a visit is abandonment. This page does not decide that a particular contractor abandoned a job. The same rules apply to a kitchen or bathroom remodel in Concord and in the rest of Contra Costa County. They are California statutes, not a city ordinance. Concord's permit rule is separate and is in the permit guide.
File a complaint with CSLB
CSLB's complaint page says homeowners, other contractors, subcontractors, and employees may file. Complaints within the board's jurisdiction include failure of a licensed contractor to fulfill the terms of an agreement. CSLB's own examples include poor workmanship, abandonment of a project, failure to pay subcontractors, material suppliers, or employees, building code violations, lack of reasonable diligence, and home improvement contract violations. The board also investigates unlicensed contracting. CSLB says it is illegal for an unlicensed person to perform contracting work on a project of $1,000 or more, including labor and materials, and that the board has jurisdiction over licensed and unlicensed projects for up to four years.
Look the license up on the CSLB license check before you file, and keep the contract, the payment records, and photos with the complaint. CSLB's page on complaints against licensed contractors says every written complaint is reviewed for jurisdiction. CSLB sends written confirmation that the complaint was received, and a notice to the contractor to encourage resolution without further CSLB action. CSLB says that while it makes every attempt to get restitution for consumers financially harmed by a licensed contractor, it cannot promise that you will get any money back.
If the complaint is not resolved, CSLB may ask for more documents. If mediation is appropriate, CSLB contacts you and the contractor and attempts to mediate. If mediation does not succeed, the contractor does not have a history of repeated acts, and the estimated financial injury is less than $12,500, CSLB says it may give you information about small claims court and about the license bond. CSLB points readers to the courts' self-help pages and the local small claims clerk for how to file. This page does not say to file a lawsuit.
If CSLB investigates, it looks for clear and convincing evidence of a violation. Citations may contain civil penalties of up to $30,000, depending on the violation, and orders of correction that can require the contractor to make repairs or to pay you to hire others to do so. CSLB says the Attorney General, if a disciplinary case is prosecuted, is counsel for CSLB, not for the person who complained.
The license bond is a separate claim
Section 7071.6 requires a contractor's bond of $25,000 as a condition of the license. Section 7071.5 says that bond is for the benefit of, among others, a homeowner contracting for home improvement on the homeowner's personal family residence who is damaged by a violation of the contractors chapter. Excluding those homeowner claims, section 7071.6 caps the surety's aggregate liability on other claims at $7,500, and reserves the rest of the bond for the homeowner beneficiaries in section 7071.5(a). That section also says a homeowner beneficiary is not barred from claiming the full bond. This page does not say a surety will pay any claim.
CSLB's bond page says the consumer contacts the surety directly. CSLB does not process claims against surety companies. The surety investigates the bond claim, and CSLB investigates the complaint against the license. Find the surety that wrote the bond in place at the time of the contract by opening "Contractor's Bond History" on the license detail page. CSLB says consumers must file with that surety within the surety's time frames. This page does not state those time frames, because they are the surety's, not a number in the statute read here.
Some contractors file a cashier's check with the state instead of a surety bond. CSLB says a consumer then has to file a civil action before CSLB can pay from that check, and that CSLB can pay only under a court order. CSLB says to email CashBonds@cslb.ca.gov first to confirm the cash deposit exists. That address is CSLB's, not this site's.
Arbitration, if CSLB refers the complaint
CSLB's licensed-contractor page says it administers a mandatory arbitration program for disputes involving alleged damages of $25,000 or less, and a voluntary program for alleged damages between $25,000 and $50,000. It also says complaints must meet stringent criteria and that CSLB staff decide whether a dispute qualifies.
Section 7085 is the statute behind that. For alleged violations of sections 7107, 7109, 7110, 7113, 7119, or 7120, the registrar may refer the dispute to arbitration with the concurrence of both the licensee and the complainant when the registrar finds the conditions in that section, including material damages. For that path, the section defines material damages as damages greater than the bond amount required by section 7071.6(a), which is $25,000, but less than $50,000. A separate paragraph says that where a possible violation of those sections exists and the contract price, or the demand for damages, is equal to or less than that bond amount, the complaint shall be referred to arbitration using the criteria the section lists, which include the public interest, no history of repeated or similar violations, a license in good standing at the time of the alleged violation, no outstanding disciplinary action, and no prior agreement to private arbitration. This page does not decide that a complaint will be referred.
Who can record a lien
Section 8400 says a person who provides work authorized for a work of improvement has a lien right, and it names the direct contractor, a subcontractor, a material supplier, an equipment lessor, a laborer, and a design professional. Paying the contractor does not, by itself, erase a lien right those other people may have. This page does not say a lien on a particular house is valid.
Section 8200 says that, before recording a lien claim, a claimant shall give preliminary notice to the owner, the direct contractor, and the construction lender if any. Compliance is a prerequisite to a valid lien claim. Two exceptions are in the same section: a laborer does not have to give preliminary notice, and a claimant with a direct contract with the owner gives preliminary notice only to the construction lender, if any.
Section 8412 says a direct contractor may not enforce a lien unless the contractor records the claim after completing the direct contract, and before the earlier of 90 days after completion of the work of improvement or 60 days after the owner records a notice of completion or cessation. Section 8414 says a claimant other than a direct contractor may not enforce a lien unless the claim is recorded after that claimant stops providing work, and before the earlier of 90 days after completion of the work of improvement or 30 days after the owner records a notice of completion or cessation. This page does not decide when a project was completed.
Section 8460 says the claimant shall start an action to enforce the lien within 90 days after the claim is recorded, or the claim expires and is unenforceable. The section has a separate rule if the claimant and the owner agree to extend credit and a notice of that extension is recorded. In that case the claimant shall start the action within 90 days after the credit ends, and in no case later than one year after completion of the work of improvement.
Section 7159.5 gives the person paying for the home improvement a related right. On any payment, and before any further payment, the contractor shall, if requested, get and furnish a full and unconditional release from any potential lien claimant or mechanics lien under Civil Code sections 8400 and 8404 for the portion of the work that payment covers. The person contracting may withhold all further payments until those releases are furnished.
Payments ahead of the work
Except for the down payment, section 7159.5 says the contractor shall not request or accept payment that exceeds the value of the work performed or the material delivered. The down payment cap, and what a 50 percent request does under that cap, is on is a 50 percent deposit normal in California. The written contract rules are in the contract guide.
What this referral will not do
Concord Remodel Guide is an independent referral service, not a contractor, and we never do the work. We do not finish a job someone else left, file a CSLB complaint, file a bond claim, or say that the first contract lets you hire someone else. The work, if you hire a contractor for it, is on kitchen remodeling and bathroom remodeling. To ask one independent licensed general contractor to follow up, use the request form.
Start a free request
Pick what you need. Five short questions.
When the contractor stops showing up
My contractor disappeared halfway through my bathroom remodel in Contra Costa County. What do I do?
Sections 7107 and 7119 do not set a number of missed days. Abandonment without legal excuse, and a wilful failure without legal excuse to keep going with reasonable diligence when that causes material injury, are causes for CSLB discipline. CSLB says a homeowner may file a complaint about abandonment or a lack of reasonable diligence, and that the board has jurisdiction for up to four years. Check the license on the CSLB license check, and keep the contract and payment records. This page does not decide that a particular contractor abandoned the job, and it is not legal advice.
How to get money back from contractor who didn't finish the job?
CSLB says it cannot promise that you will get any money back. A complaint can lead to mediation, and in some cases CSLB gives information about small claims court and the license bond. The bond claim is filed with the surety named on the license's Contractor's Bond History, not with CSLB. The bond amount in section 7071.6 is $25,000. A homeowner who fits section 7071.5(a) is a beneficiary. This page does not say a surety or a court will pay.
What if the contractor stops showing up but has not walked off in writing?
Section 7107 uses "abandonment without legal excuse." Section 7119 uses a wilful failure or refusal, without legal excuse, to prosecute the project with reasonable diligence, causing material injury. Neither section requires a written resignation, and neither counts a number of days. CSLB lists both abandonment and lack of reasonable diligence as complaint grounds. This page does not decide which label fits one job.
Can a subcontractor record a lien if I already paid the contractor?
Section 8400 gives a subcontractor, a material supplier, and others a lien right for work authorized for the improvement. Payment to the direct contractor does not, by itself, remove that right. Section 8200 requires preliminary notice before a lien claim, with exceptions for a laborer and for a claimant who contracted directly with the owner. Section 7159.5 says you may ask the contractor for full unconditional releases for the portion you paid, and you may withhold further payments until those releases are furnished. This page does not say a lien on your house is valid.
Sources
- California Business and Professions Code section 7107, abandonment, read October 31, 2026
- California Business and Professions Code section 7113, failure to complete for the price stated, read October 31, 2026
- California Business and Professions Code section 7119, failure to prosecute with reasonable diligence, read October 31, 2026
- California Business and Professions Code section 7085, CSLB arbitration, read October 31, 2026
- California Business and Professions Code section 7071.5, who the contractor bond benefits, read October 31, 2026
- California Business and Professions Code section 7071.6, contractor bond amount, read October 31, 2026
- California Business and Professions Code section 7159.5
- CSLB, How the complaint process works, read October 31, 2026
- CSLB, Complaint process against licensed contractors, read October 31, 2026
- CSLB, Bond basics, including how to file a bond claim, read October 31, 2026
- Contractors State License Board license lookup
- California Civil Code section 8400, who has a mechanics lien right, read October 31, 2026
- California Civil Code section 8200, preliminary notice, read October 31, 2026
- California Civil Code section 8412, when a direct contractor may enforce a lien, read October 31, 2026
- California Civil Code section 8414, when another claimant may enforce a lien, read October 31, 2026
- California Civil Code section 8460, time to enforce a recorded lien, read October 31, 2026
Ask a licensed general contractor to follow up
Call or send a request with your address and whether this is a kitchen, a bathroom, or both. We pass your request to one independent licensed general contractor who serves Concord, CA, if one is available.