Who is supplying the finishes on my kitchen or bathroom remodel?

Labor-only and all-in bids are not the same bid. What California law requires the contract to say about materials, no matter who is buying them.

Published November 18, 2026. Reviewed against public sources listed below.

Who is supplying the finishes on my Concord remodel?

Either side can buy the cabinets, tile, counters, and fixtures. Some bids are "labor only," where you buy and deliver every finish yourself, and some are "all in," where the contractor sources everything and bills it as part of the contract price. A lot of bid confusion traces back to this one question, since a labor-only number and an all-in number for the same kitchen can look wildly different while describing the same scope of work. Neither arrangement changes what the law requires of the written contract, and neither one removes the risk that a material supplier who is not paid can still have a lien right against the house, whoever placed the order.

What the contract has to say about materials, no matter who buys them

California Business and Professions Code section 7159 requires a written home improvement contract for a Concord remodel over $500, and that contract has to include a description of the project and the significant materials and equipment, on top of the contractor's license number, the price in dollars and cents, start and completion dates, and the other items the section lists. A bid that just says "materials" with no detail does not meet that bar, whether the contractor is supplying those materials or you are. If you are supplying the finishes yourself, ask the contractor to still list them by name in the contract, with an allowance or credit if the price assumed a certain cost, so the written scope matches what is actually going into the house.

A supplier's lien right does not depend on who ordered the tile

Civil Code section 8400 gives a lien right to a person who provides work authorized for a work of improvement, and names the direct contractor, a subcontractor, a material supplier, an equipment lessor, a laborer, and a design professional. Paying the general contractor in full does not, by itself, erase a lien right that a material supplier or subcontractor may still have if the contractor never paid that supplier. Section 8200 requires a claimant to give preliminary notice to the owner, the direct contractor, and the construction lender, if any, before recording a lien claim, with exceptions for a laborer and for a claimant who contracted directly with the owner. That notice requirement is also your early warning: a supplier who sends you a preliminary notice is telling you it is in the job, which matters whether the contractor or you placed that order.

Ask for the release, whoever bought the finishes

Section 7159.5 gives the person paying for the remodel a direct tool: on any payment, and before any further payment, you may ask the contractor to get and furnish a full, unconditional release from any potential lien claimant for the portion of the work that payment covers, and you may withhold further payment until that release is furnished. That tool works the same way whether the contractor supplied the finishes as part of an all-in price, or you bought them yourself and the release only needs to cover labor and installation. CSLB's own complaint page lists failure to pay subcontractors, material suppliers, or employees as an example of what falls within the board's jurisdiction, which is a reason to keep the releases on file along with the contract and the payment records, not just the receipts for what you bought yourself.

Owner-supplied versus contractor-supplied finishes

Does the contract have to list materials if I am supplying the finishes myself?

Yes. Business and Professions Code section 7159 requires a description of the project and the significant materials and equipment in the written contract, regardless of who is buying them. Ask for an allowance or credit line if the price assumed a certain cost for items you are supplying.

If I already paid the contractor, can a material supplier still put a lien on my house?

Civil Code section 8400 gives a material supplier, among others, a lien right for work authorized for the improvement. Paying the contractor does not, by itself, remove that right if the contractor never paid the supplier.

How do I protect myself from a lien when I pay for finishes through the contractor?

Section 7159.5 lets you ask the contractor for a full, unconditional lien release for the portion any payment covers, and lets you withhold further payment until that release is furnished.

Does a supplier have to warn me before filing a lien?

Usually. Civil Code section 8200 requires preliminary notice to the owner, the direct contractor, and the construction lender if any, before a lien claim, with exceptions for a laborer and a claimant who contracted directly with the owner.

Ask a licensed general contractor to follow up

Call or send a request with your address and whether this is a kitchen, a bathroom, or both. We pass your request to one independent licensed general contractor who serves Concord, CA, if one is available.